Common mistakes in the planning and operation of pigging systems
Many faults in pigging systems are caused not by the pig, but by planning, pipeline installation or the control system. The most common ones can be avoided with a few rules.
During planning
- The compatibility of the products with each other and the resistance of the pig material are not tested. This is one of the most common causes of later problems.
- Pipeline, stations and control system are contracted separately, and nobody is responsible for how they work together.
- The sequence is not defined step by step before stations and valves are selected.
During pipeline installation
A trial pig run with water before commissioning reveals many of these faults.
- Misalignment at welds, excessive root penetration, oval pipe ends
- Gaskets or pipe ends protruding into the cross-section
- Weld spatter or loose parts that damage the pig on its first run
In operation
During commissioning, errors in the control software are a frequent source of faults. A properly documented sequence with step transition conditions helps to find them early.
- Pig is not detected: usually a misaligned or defective detector; sometimes the pig has been pulled out of its end position by pumping or by expanding air.
- Pig moves in jerks: often the supply air was throttled instead of the exhaust air, or the pig is running dry.
- Pig gets stuck: weld, valve in an intermediate position, worn pig or lack of propellant.
- Product discharge deteriorates: pig wear; check the minimum diameter.
Technical basis in addition to our own documentation: G. Hiltscher, W. Mühlthaler, J. Smits: Molchtechnik. Grundlagen, Komponenten, Anwendungstechnik [Pigging technology: fundamentals, components, application engineering; in German]. Wiley-VCH, Weinheim 1999. Information reproduced in substance; guide values from the literature do not replace a case-by-case design.